# City of Meadow
> **Administrative - Formal** · FY2011 · — · Final Order No Penalty
## Case
- **Activity ID:** `2600040260`
- **Case Number:** 06-2011-1376
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Charles Jessup (settlement)
- City of Meadow (complaint) (settlement)
## Summary

Respondent was issued an Administrative Order on July 19, 2011 for failure to comply with the arsenic MCL.  Within 120 days, Respondent is required to submit to EPA a detailed report to bring the PWS into compliance with the MLC for arsenic.

---