← EPA enforcement cases

Max Foote Construction Co., Inc. (General Contractors)

Administrative - Formal · FY2011 · — · Unilateral Administrative Order Without Adjudication · 2600068896

Penalty
Cost recovery
Compliance action

Case

Case Number
06-2011-1870
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
Self-disclosure
N

Defendants (2)

Summary

Respondent, Max Foote Construction Company owned or operated a construction site located in St. Bernard Parish, Louisiana. Respondent failed to comply with the LPDES Storm Water Program requirement in not obtaining a storm water permit.

Source

Authoritative
EPA ECHO
Machine