# C.D. MOODY CONSTRUCTION COMPANY, INC.
> **Administrative - Formal** · FY2012 · — · Final Order With Penalty
## Case
- **Activity ID:** `2600075713`
- **Case Number:** 04-2012-1502
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- C.D. MOODY CONSTRUCTION COMPANY, INC. (complaint) (settlement)
## Summary

11/17/2011 - CONSENT AGREEMENT AND FINAL ORDER ISSUED, ASSESSING A PENALTY OF $6,373. RESPONDENT SHALL MAKE PAYMENT WITHIN THIRTY DAYS.

ORDER ALLEGES:
 DEMOLITION  OCCURRED BETWEEN MAY 5, 2011, AND MAY 8, 2011, AT A  FACILITY  FORMERLY LOCATED AT 400 0AK STREET SOUTHWEST IN EASTMAN, GEORGIA (THE FACILITY).

THE FACILITY BEING DEMOLISHED WAS A SINGLE COMMERCIAL BUILDING THAT HAD BEEN USED AS A MCDONALD'S RESTAURANT.

RESPONDENT OWNED, LEASED, OPERATED, CONTROLLED OR SUPERVISED THE DEMOLITION OPERATION AT THE FACILITY.

RESPONDENT IS THEREFORE AN  OWNER OR OPERATOR OF A RENOVATION OR DEMOLITION ACTIVITY. 

RESPONDENT VIOLATED SECTION 112 OF THE CAA, 42 U.S.C. SECTION 7412, AND 40 CFR SECTION 61.145(b) BY FAILING TO PROVIDE THE STATE OF GEORGIA WITH WRITTEN NOTICE OF INTENTION TO DEMOLISH THE FACILITY.

---