Summary

<<<NOVEMBER, 1986 ENTRIES>>> 10/10/86: MOTION FOR EXTENSION ON PRE-HEARING EXCHANGE STATUS REPORT. NOTICE OF SUBSTITUTION OF COUNSEL. 10/23/86: MOTION GRANTERD BY JUDGE HARWOOD UNTIL NOVEM- BER 10, 1986. 10/25/86: ROBERT HOGAN OPP. COUNSEL, ASKED FOR EXTENSION ON PRE-HEARING EXCHANGE DATE UNTIL NOVEMBER 21, 1986. 10/29/86: STRATEGY MEETING WITH GREG CZAJKOWSKI - BEGIN TO DRAFT CAFO WITH SCHEDULE - PLAN TO MEET WITH HOGAN DURING THE WEEK OF NOVEMBER 17, 1986. 11/4/86: JUDGE HARWOOD GRANTED HOGAN'S REQUEST FOR EX- TENSION UNTIL NOVEMBER 21, 1986 - PRE-HEARING EXCHANGE.