# FRANKLIN IRON AND METAL
> **Administrative - Formal** · FY1987 · — · Final Order With Penalty
## Case
- **Activity ID:** `26434`
- **Case Number:** 05-1987-0197
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** $3K
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- FRANKLIN IRON AND METAL (complaint) (settlement)
## Summary

THE SOIL SAMPLE OBTAINED NEAR THE ALUMINUM RECYCLE BUILDING  ANALYZES TO BE 81 PPM PCB'S AND THE SOIL SAMPLE OBTAINED     NEAR THE BOILER SHEAR BUILDING ANALYZED TO BE 247 PPM PCB'S. COMPANY OFFICIALS INDICATED THAT THE ONLY DRAINED PCB CON-   TAMINATED TRANSFORMERS WERE BROUGHT ON SITE IN 1984.  PAST   TRANSFORMER ACTIVITY TOOK LACE IN THE BOILER SHEAR BUILDING. ONE OF THE TASKS TO BE COMPLETED IS ESTABLISHING THE AGENCY  OF THE PCB'S.

---