# LIQUID DYNAMICS
> **Administrative - Formal** · FY1988 · — · Final Order With Penalty
## Case
- **Activity ID:** `27024`
- **Case Number:** 05-1988-0328
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** $57K
- **Cost recovery:** $0
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- ACCUTRONICS (complaint) (settlement)
- ACME GALVANIZING (complaint) (settlement)
- ALLIED TUBE & CONDUIT (complaint) (settlement)
- AMERICAN WASTE PROCESSING (complaint) (settlement)
- ASHLAND CHEMICAL (complaint) (settlement)
- BRIGHTLY GALVANIZED PODUCTS (complaint) (settlement)
- CHGO TRIBUNE (complaint) (settlement)
- COPPERWELD TUBING (complaint) (settlement)
- GENERAL TUBE (complaint) (settlement)
- H H HOWARD (complaint) (settlement)
- KAISER ALUMINUM
- MID-WEST
- OUTBOARD MARINE
- PANDUIT
- ROLLINS LEASING
- VERSON ALLSTEEL PRESS
- WAYNE CIRCUITS
- ZENITH
## Summary

EMERGENCY REMOVAL ORIGINALLY DONE AT SITE FROM APRIL TO    JUNE 1983.  HOWEVER, TWO TANKS CONTAINING APPROX 30,000 GAL- LONS OF MATERIAL EACH WERE LEFT ON SITE.  THIS REMOVAL WOULD INVOLVE REMOVING AND DISPOSING OF THAT REMAINING MATERIAL.     A COST RECOVERY ACTION WAS BROUGHT AGAINST PRPS IN CONNECT TION WITH EARLIER REMOVAL.  A SETTLEMENT WAS REACHED AND A   CONSENT DECREE WAS ENTERED BY THE PARTIES.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*