THE BUCKEYE RECLAMATION SITE WAS OPERATED AS A LANDFILL FOR SOLID WASTE AND AT CERTAIN TIMES FOR HAZARDOUS WASTE. AN RI/FS WAS CONDUCTED AT THE SITE AND A ROD REQUIRING A CAP. LEACHATE CONTROLS AND TREATMENT, AND LONG TERM MONITORING OF THE GROUND WATER WAS ISSUED IN 1991. AFTER A 90 DAY NEGOTIATING PERIOD IT WAS AGREED THAT A GROUP OF THE PRPS WOULD CONDUCT A REMEDIAL DESIGN. THE ANTICIPATED COST FOR THE REMEDIAL ACTION IS APPROXIMATELY 40 MILLION DOLLLARS.