# PITSCH ENGINEERING
> **Administrative - Formal** · FY1993 · — · Final Order No Penalty
## Case
- **Activity ID:** `28213`
- **Case Number:** 05-1993-0225
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** $0
- **Cost recovery:** $0
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- GRAVEL (DEMOLITION CONTRACTOR)
- PINE REST CARESTION HOSPITAL
- RIVERSIDE SAND
## Summary

THESE ARE TWO CASES, WITH PITSCH ENGINEERING AS THE        ASBESTOS ABATEMENT CONTRACTOR IN EACH CASE.   IN THE FIRST   CASE, A FINDING OF VIOLATION (FOV) WAS ISSUED ON 10/15/92 TO PITSCH, AS WELL AS PINE REST CARESTION HOSPITAL (OWNER) AND  RIVERSIDE SAND AND GRAVEL (DEMOLITION CONTRACTOR) FOR        VIOLATION OF WORK PRACTICE STANDARDS AT 40 CPR 61.147(E) AND (E). IN THE SECOND, AN FOV WAS ISSUED TO PITSCH, AS WELL AS  TO FORD PETOSKEY BUILDING (OWNER) AND DUNBAR EXCAVATION      (DEMOLITION CONTRACTOR).                                     11/12/92 SECTION 113 CONFERENCE W/PITSCH + DUNBAR.           11/18/92 SECTION 113 CONFERENCE W/PINE REST HOSPITAL +       RIVERSIDE SAND.                                              11/25/92 COMPANIES SUBMIT INFORMATION.                       R

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*