# MURPHY ENGINEERING COMPANY
> **Administrative - Formal** · FY1993 · — · Final Order With Penalty
## Case
- **Activity ID:** `28253`
- **Case Number:** 05-1993-0469
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** $2K
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- MURPHY ENGINEERING COMPANY (complaint) (settlement)
## Summary

ON FEBRUARY 23, 1993,  U.S. EPA FILED A RCRA             ADMINISTRATIVE COMPLAINT AGAINST MURPHY ENGINEERING FOR      STORING A RCRA HAZARDOUS WASTE (F019) IN EXCESS OF ONE 180 - DAYS ALLOWED BY 40 C.F.R. SECTION 262.34(D).  MURPHY STORED  F019 IN VIOLATION OF RCRA FROM FEBRUARY 5, 1991 TO AT LEAST  MAY 8, 1992.  MURPHY'S ANSWER IS EXPECTED ON MARCH 25, 1993.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*