← EPA enforcement cases

LOUISIANA PACIFIC, INC/HAYWARD, WI

Judicial · FY1993 · — · Final Order No Penalty · 28285

$0
Penalty
$0
Cost recovery
Compliance action

Case

Case Number
05-1993-0534
Type
Judicial
Lead
EPA
Outcome
Final Order No Penalty
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

LOUISANA PACIFIC, INC. LINE II HAS FAILED TO OBTAIN A PSD PERMIT AS REQUIRED BY THE PSD REGULATIONS. STATUTORY AND REGULATORY BASIS FOR ACTION: 42 U.S.C. SECTION 7407, AND SECTION 7475 AND 40 C.F.R. SECTION 52.21. VIOLATIONS: 42 U.S.C. SECTION 7475 AND 40 C.F.R. PART 52.21 FOR FAILURE TO OBTAIN PSD PERMIT FOR MAJOR MODIFICATION TO A APPLY FOR PSD PERMIT WAS A VIOLATION OF CONSENT DECREE NO. 89C-0337S. PROPOSED RELIEF: U.S. EPA, REGION V SEEKS INJUNCTIVE RELIEF WHICH WOULD PROVIDE FOR THE INSTALLATION OF BACT AT HAYWARD LINE II. CIVIL PENALTY FOR THIS ACTION WILL BE COLLECTED AS PART OF THE SETTLEMENT RESOLVING THE STATE ACTION AGAINST LPC. THE STATE IF WISCONSIN FILED A LAWSUIT AGAINST HAYWARD ON OCTOBER 16, 1992 FOR FAILURE TO OBTAIN A PSD PERMIT FOR HAYWARD II AND FOR OPERATING PERMIT VIOLATIONS (VOC AND OPERATIONAL LIMITS). JULY 3, 1991, SECTION 114 REQUEST FOR INFORMATION. DECEMBER 2, 1991, SECTION 114 REQUEST FOR INFORMATION. JULY 31, 1992, NOTIVE OF VIOLATION (DID NOT NAME HAYWARD FACILTY). U.S. EPA AND DEPARTMENT OF JUSTICE HAVE MET WITH LPC OFFICIALS ON SEVERAL OCCASIONS TO DISCUSS SETTLEMENT OF THE NATIONAL LAWSUIT.

Source

Authoritative
EPA ECHO