← EPA enforcement cases

CIW

Judicial · FY1993 · — · Final Order With Specified Cost Recovery · 28391

Penalty
$155K
Cost recovery
Compliance action

Case

Case Number
05-1993-0835
Type
Judicial
Lead
EPA
Outcome
Final Order With Specified Cost Recovery
Multimedia
N
Self-disclosure
N

Defendants (5)

Summary

THIS CASE INVOLVED A REFERRAL SENT TO U.S. DOJ FOR COLLECTION OF PAST COSTS EXPENDED UNDER THE SUPERFUND BY U.S. EPA TO COMPLETE A CLEAN UP AT THE CIW CO. SITE. THE PRP'S WERE TRANSPORTERS, OPERATORS AND GENERATORS. THE HAZARDOUS MATERIALS INCLUDED PCB'S AND HEAVY METALS. UPON NEGOTIATIONS BETWEEN THE PRP'S AND EPA/DOJ, A SETTLEMENT WAS REACHED. THE SETTLEMENT WAS SIGNED BY THE PARTIES IN JULY 1995, AND AWAITS LODGING IN THE FEDERAL DISTRICT COURT. THE CASE WAS LODGED IN OCTOBER 1995, AND THE COURT ENTERED IT ON DECEMBER 4, 1995.

Source

Authoritative
EPA ECHO