# OTT/STORY/CORDOVA CHEMICAL
> **Administrative - Formal** · FY1993 · — · Final Order No Penalty
## Case
- **Activity ID:** `28472`
- **Case Number:** 05-1993-1185
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** $0
- **Cost recovery:** $0
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- AEROJET-GENERAL CORPORATION (complaint)
- CORDOVA CHEMICAL COMPANY OF CALIFORNIA (complaint)
- CORDOVA CHEMICAL COMPANY OF MICHIGAN (complaint)
- CPC INTERNATIONAL, INC. (complaint)
## Summary

THIS UAO MODIFICATION WAS ISSUED TO TERMINATE ANY FURTHER    REMEDIAL ACTION WORK AT THE SITE BY THE RESPONDENTS.         RESPONDENTS HAD CLAIMED AUTHORITY TO DO SUCH WORK UNDER      EARLIER UAOS ISSUED IN MARCH 20, 1990 (DOCKET NO.            V-W-90-C-049). SEE MATTER NUMBERS 05-93-1184 AND 1186. THE   UAO MODIFICATION HAS BEEN COMPLIED WITH BY THE RESPONDENTS.

---