U.S. EPA CONDUCTED A FUND-FINANCED TIME-CRITICAL REMOVAL ACTION FROM NOVEMBER 2, 1990 THROUGH OCTOBER 23, 1991. PRPS INCLUDE DELTED, INC., THE SITE PROPERTY OWNER; MR. CHROME CORP. AND RICHARD SHAW, SITE OPERATORS. NONE OF THE PRPS COMPLIED WITH A UNILATERAL ADMINISTRATIVE ORDER ISSUED OCTOBER 2, 1989. US EPA PERFECTED A LIEN AGAINST THE SUBJECT PROPERTY MAY 16, 1991. THIS LIEN WAS SUBSEQUENTLY PARTIALLY RELEASED TWICE TO CORRECT DISCREPANCIES IN THE PROPERTY DESCRIPTIONS OF THE ORIGINAL LIEN.