← EPA enforcement cases

WOLVERINE ENVIRONMENTAL PRODUCTION, INC.

Administrative - Formal · FY1993 · — · Final Order With Penalty · 28663

$2K
Penalty
$0
Cost recovery
Compliance action

Case

Case Number
05-1993-1556
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

RESPONDENT OBTAINED PERMIT TO CONSTRUCT WELL. PERMIT EXPIRED WHEN RESPONDENT DID NOT COMMENCE CONSTRUCTION W/IN ONE YEAR AFTER IT EXPIRED, AND BEFORE RESPONDENT OBTAINED A NEW PERMIT, RESPONDENT CONSTRUCTED THE WELL. THUS, VIOLATION ALLEGED WAS CONSTRUCTION WITHOUT A PERMIT. PENALTY SOUGHT $4,500 AND SETTLED FOR $2,100 FINAL ADMINISTRATIVE CONSENT ORDER FILED WITH REGIONAL HEARING CLERK ON 09/16/93.

Source

Authoritative
EPA ECHO
Machine