# CARDINAL ENVIRONMENTAL SERVICES, INC.
> **Judicial** · FY1995 · — · Final Order With Penalty
## Case
- **Activity ID:** `29181`
- **Case Number:** 05-1995-0164
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** $5K
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- CARDINAL ENVIRONMENTAL SERVICES, INC. (settlement)
## Summary

AN INSPECTION OF AN ASBESTOS REMOVAL JOB AT THE BARBERTON    CITIZENS HOSPITAL, ON SEPTEMBER 15, 1995, REVEALED WORK      PRACTICE VIOLATIONS OF THE ASBESTOS NESHAP, FOR CARDINAL'S   FAILURE TO WET AND KEEP WET THE ASBESTOS MATERIAL, PRIOR TO  IT BEING LAWFULLY DISPOSED OF.  FURTHER INQUIRY REVEALED     THAT ALL REQUIRED INFORMATION WAS NOT PROVIDED BY CARDINAL   ON ITS NOTICE OF INTENT TO RENOVATE, AND THAT, IN SHIPPING   THE ASBESTOS REMOVED FROM THE RENOVATION SITE TO THE         DISPOSAL SITE, CARDINAL DID NOT PREPARE AND MAINTAIN THE     REQUIRED MANIFEST DOCUMENTATION.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*