# ALBION SHERIDAN TOWNSHIP LANDFILL
> **Judicial** · FY1995 · — · —
## Case
- **Activity ID:** `29202`
- **Case Number:** 05-1995-0187
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** —
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** $3.00M
- **Multimedia (multi-env):** N
## Defendants
- ALBION, CITY OF (settlement)
- COOPER INDUSTRIES (complaint) (settlement)
- CORNING INC. (complaint) (settlement)
- DECKER MANUFACTURING (settlement)
## Summary

THIS SITE IS A MUNICIPAL LANDFILL.  A REMOVAL, UNDER A UAO   WAS COMPLETED IN 1990.  THE AGENCY CONDUCTED AN RI/FS IN     1991.  THE ROD WAS SIGNED ON 3/28/95.  THE PRE-REFERRAL      LITIGATION PACKAGE WAS SENT TO DOJ ON 3/13/95.

---