CROSS BROTHERS PAIL RECYCLING SITE

Administrative - Formal · FY1995 · — · Final Order No Penalty · 29387

$0
Penalty
$0
Cost recovery
Compliance action

Case

Case Number
05-1995-0418
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order No Penalty
Multimedia
N
Self-disclosure
N

Defendants (6)

Summary

THIS UAO WAS ISSUED TO IMPLEMENT A ROD ISSUED 9/28/89 TO RECOVER RESPONSE COSTS. THE RESPONDENTS COMPLETED REMEDIAL DESIGN BUT FAILED TO START REMEDIAL ACTION IN JANUARY 1991 AS REQUIRED, 2 RESPONDENTS STARTED RA IN MAY 1995.