H. FRED LEVINE, ET AL./ENTERPRISE OIL

Judicial · FY1996 · — · Final Order With Specified Cost Recovery · 29807

Penalty
$690K
Cost recovery
Compliance action

Case

Case Number
05-1996-0374
Type
Judicial
Lead
EPA
Outcome
Final Order With Specified Cost Recovery
Multimedia
N
Self-disclosure
N

Defendants (14)

Summary

MORECO ENERGY INC., OPERATED A USED OIL STORAGE AND TRANSFER FACILITY AT THE SITE FROM MARCH 1988 THROUGH THE END OF DECEMBER 1988 OR EARLY JANUARY 1989, WHEN THE SITE WAS ABANDONED. EPA PERFORMED A REMOVAL ACTION AT THE SITE BEGINNING ON OR ABOUT JUNE 15, 1992, AND ENDING ON OR ABOUT OCTOBER 1, 1993. ALL PRPS LISTED WERE GENERATORS WHOSE USED OIL WAS SENT TO THE SITE, WITH THE EXCEPTION OF MR. LEVINE WHO HELD TITLE TO THE PROPERTY DURING THE PERIOD OF OPERATIONS.