5/3/2012 - CONSENT AGREEMENT AND FINAL ORDER ISSUED, ASSESSING A PENALTY OF $70,000. RESPONDENT SHALL MAKE PAYMENT WITHIN THIRTY DAYS.
ORDER ALLEGES:
COMMENCING ON OR ABOUT AUGUST 2010, RESPONDENT, OR THOSE ACTING ON BEHALF OF THE RESPONDENT, INADVERTENTLY DISCHARGED DREDGED AND/OR FILL MATERIAL WITHOUT AUTHORIZATION INTO A WETLAND AND TRIBUTARY ON THE SITE USING EARTH MOVING MACHINERY, DURING ACTIVITIES ASSOCIATED WITH THE EXPANSION OF A TAXIWAY.
RESPONDENT IMPACTED APPROXIMATELY 0.05 ACRES OF WETLANDS AND 200 LINEAR FEET OF AN UNNAMED TRIBUTARY (DISCHARGE AREA) TO SUGAR CREEK THAT FLOWS TO THE CATAWBA RIVER, A NAVIGABLE WATER OF THE UNITED STATES.