# UNION CARBIDE CORP. MARIETTA FACILITY
> **Administrative - Formal** · FY1997 · — · Final Order With Specified Cost Recovery
## Case
- **Activity ID:** `30137`
- **Case Number:** 05-1997-0131
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Specified Cost Recovery
- **Penalty assessed:** —
- **Cost recovery:** $614K
- **Compliance action $:** $54.00M
- **Multimedia (multi-env):** N
## Defendants
- UNION CARBIDE CORP. MARIETTA FACILITY (complaint) (settlement)
## Summary

THE WORK REQUIRED BY THE ADMINISTRATIVE ORDER BY CONSENT     INCLUDES THE FOLLOWING COMPONENTS; EXCAVATION AND            CONSOLIDATION OF DIOXIN-CONTAMINATED SOILS; EXCAVATION AND   CONSOLIDATION OR IN SITU SOIL VAPOR EXTRACTION OF            VOC-CONTAMINATED SOILS; HAZARDOUS WASTE CAPS FOR THE TWO     LANDFILLS ON-SITE; A BOTTOM LINER FOR A PORTION OF ONE OF    THE LANDFILLS; A HYDRAULIC BARRIER AROUND THE WASTE AREA     THAT IS THE MAIN SOURCE OF GROUNDWATER CONTAMINATION;        EXCAVATION AND ON-SITE CONSOLIDATION OF CONTAMINATED         SEDIMENTS IN A CREEK RUNNING THROUGH THE SITE; INSTALLATION  OF A CONCRETE CULVERT, AND CREEK BANK STABILIZATION;         CONTAINMENT AND TREATMENT OF CONTAMINATED GROUNDWATER; AND   ACCESS AND DEED RESTRICTIONS.

---