# AUTOZONE, INC.
> **Administrative - Formal** · FY1997 · — · Final Order With Penalty
## Case
- **Activity ID:** `30245`
- **Case Number:** 05-1997-0283
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** $21K
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- AUTOZONE, INC. (complaint) (settlement)
- CRAWFORD CO. (settlement)
- ZOCOLO EXCAVATING
## Summary

FAILURE TO COMPLY WITH ASBESTOS NESHAP, 40 CFR SEC.          61.145(B)(3): FAILURE TO PROVIDE THE ADMINISTRATOR WITH      WRITTEN NOTICE OF INTENT TO DEMOLISH AT LEAST 10 WORKING     DAYS BEFORE DEMOLITION BEGINS.                               CACO FILED 9/16/97, SETTLING COMPLAINT FOR $21,250 PAID      BY 2 PARTIES: AUTOZONE, INC. AND RE CRAWFORD.

---