# ROTO-FINISH/ILL. TOOL/SLEZAK
> **Judicial** · FY1997 · — · Final Order With Specified Cost Recovery
## Case
- **Activity ID:** `30284`
- **Case Number:** 05-1997-0344
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Specified Cost Recovery
- **Penalty assessed:** —
- **Cost recovery:** $724K
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- ILLINOIS TOOL WORKS INC. (complaint) (settlement)
- SLEZAK ENTERPRISES (complaint) (settlement)
## Summary

THE U.S. IS SEEKING IMPLEMENTATION OF THE ROD SIGNED FOR THE ROTO-FINISH SITE ON MARCH 31, 1997. THE ROD CALLS FOR MONITO RED NATURAL ATTENUATION AND A CONTINGENCY REMEDY AND INSTITU TIONAL CONTROLS. U.S. EPA SENT SPEDIAL NOTICE LETTERS ON     JULY 31, 1997, TO THE TWO PRP'S LISTED; NEGOTIATIONS BEGAN   FOR IMPLEMENTATION OF THE REMEDY AND THE PAYMENT OF PAST     COSTS ON AUGUST 20, 1997. THE DROP DEAD DATE WHEN A GOOD     FAITH OFFER IS DUE IS OCTOBER 3, 1997.

---