# ALL SEASON'S ROOFING (SAME CASE AS PURDUE)
> **Administrative - Formal** · FY1997 · — · Final Order With Penalty
## Case
- **Activity ID:** `30378`
- **Case Number:** 05-1997-0456
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** $8K
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- ALL SEASON'S ROOFING (complaint) (settlement)
## Summary

THE COMPLAINT, FILED ON OCTOBER 13, 1993, PURSUANT TO SECTIO N 113 OF THE CAA, ALLEGED THAT ALL SEANS AND PURDUE UNIVERSI TY VIOLATED THE CAA IN THE RESPONDENT'S FAILED TO CONDUCT A  THOROUGH INSPECTION; FAILED TO NOTIFY ON TIME; FAILED TO ADE QUATELY WET THE REGULATED ASBESTOS-CONTAINING MATERIAL ( RAC M) PRIOR TO REMOVAL; FAILED TO STRIP OR CONTAIN RACM; FAILED TO KEEP RACM WET WHILE AWAITING DISPOSAL; AND FAILED TO HAVE AN ON-SITE TRAINEE AND CREDENTIALS AT THE RENOVATION SITE, A LL IN VIOLATION OF THE ASBESTOS NESHAP.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*