# MAINE DEPARTMENT OF TRANSPORTATION
> **Judicial** · FY1995 · — · Final Order With Penalty
## Case
- **Activity ID:** `308`
- **Case Number:** 01-1995-0001
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** $10K
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- BRIDGECORP (complaint) (settlement)
- DALE HENDERSON LOGGING INC (complaint) (settlement)
- MAINE DEPARTMENT OF TRANSPORTATION (complaint) (settlement)
- ROBERT WARDWELL & SONS INC (complaint) (settlement)
- TY LIN INTERNATIONAL (complaint) (settlement)
## Summary

THE PROPOSED DEFENDANTS FILLED AND DISTURBED APPROXIMATELY   10.1 ACRES OF FRESHWATER WETLANDS WITHOUT FEDERAL PERMIT ON  SEARS ISLAND, SEARSPORT, MAINE IN 1985, IN ORDER TO          CONSTRUCT AN ACCESS ROAD AND TO CLEAR, LEVEL AND PREPARE AN  AREA FOR CONSTRUCTION OF A MARINE DRY CARGO TERMINAL.

---