# PRO-TEC COATING COMPANY
> **Judicial** · FY1998 · — · Final Order With Penalty
## Case
- **Activity ID:** `30960`
- **Case Number:** 05-1998-0358
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** $1.05M
- **Cost recovery:** —
- **Compliance action $:** $5.00M
- **Multimedia (multi-env):** N
## Defendants
- PRO-TEC COATING COMPANY (settlement)
## Summary

PRO-TEC COATING COMPANY IS THE OPERATOR OF AN EXISTING       CONTINUOUS HOT DIP STEEL COIL GALVANIZING LINE (CGL#1) AND   IS CONSTRUCTING A NEW CONTINUOUS HOT DIP STEEL COIL GALVAN-  IZING LINE (CGL#2) AT ITS FACILITY.  PRO-TEC BEGAN CONSTRU-  CTION OF CGL #2 WITHOUT THE REQUIRED PERMIT TO INSTALL, IN   VIOLATION OF THE CLEAN AIR ACT, THE FEDERAL REGULATIONS AND  THE OHIO SIP.  BOTH CGL #1 IS A MAJOR SOURCE AND CGL #2 IS A MAJOR MODIFICATION OF A MAJOR SOURCE.  PRO-TEC FAILED TO     EMPLOY BACT AT CGL #1 AND CGL #2.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*