# IROQUOIS FOUNDRY
> **Administrative - Formal** · FY1999 · — · Final Order No Penalty
## Case
- **Activity ID:** `31522`
- **Case Number:** 05-1999-0155
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** $130K
- **Multimedia (multi-env):** N
## Defendants
- IROQUOIS FOUNDRY (settlement)
## Summary

IROQUOIS FOUNDRY PRODUCES GREY IRON CASTINGS FROM SCRAP      METAL.  EMISSION SOURCES AT THE PLANT INCLUDE A CUPOLA       FURNACE WHICH WAS INSTALLED IN 1978.  INSPECTIONS CONDUCTED  BY THE STATE IN 1997, DOCUMENTED VIOLATIONS OF OPACITY AND   CARBON MONOXIDE (CO) REGULATIONS AT THE CUPOLA.  STACK TESTS CONDUCTED IN RESPONSE TO USEPA'S REQUEST ALSO SHOWED         EXCEEDANCES OF THE PM LIMITS CONTAINED IN THE WISCONSIN SIP. TO COMPLY WITH THE CO AND PM LIMITS, IROQUOIS INSTALLED AN   AFTER BURNER FOR THE CUPOLA AND UPGRADED THE VENTURI         SCRUBBER SYSTEM.  THIS CASE WAS RESOLVED BY ISSURING A CACO  AND A 113(A) ORDER.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*