# BECKERS CONSTRUCTION CO., INC.
> **Administrative - Formal** · FY1999 · — · Final Order With Penalty
## Case
- **Activity ID:** `31575`
- **Case Number:** 05-1999-0220
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** $450
- **Cost recovery:** —
- **Compliance action $:** $0
- **Multimedia (multi-env):** N
## Defendants
- BECKER CONSTRUCTION CO., INC. (settlement)
## Summary

COMPLIANCE ACTIONS:                                          - OWNER PROPERLY CLOSED ALL USTS AT THE FACILITY.            - NOTIFICATION OF UST REMOVAL WAS SENT TO THE STATE.         - A SIGNED COPY OF THE NOTIFICATION WAS FAXED TO REGION 5.   - DATE OF TANKS REMOVAL: 10/14/98.                           - OWNER SIGNED THE COMPLIANCE ORDER/SETTLEMENT AGREEMENT ON  11/23/98 AND FORWARDED THE ORIGINAL COPY TO REGION 5 WITH    THE CHECK OF $450.00.

---