← EPA enforcement cases

PRECISION CHROME, INC.

Administrative - Formal · FY1999 · — · Final Order No Penalty · 31585

Penalty
Cost recovery
$871K
Compliance action

Case

Case Number
05-1999-0235
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order No Penalty
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

THE SITE WAS OWNED AND OPERATED BY A MAN RUMMING THIS OWN BUSINESS WHO ACCEPTED SPENT PLATING WASTE (CHROMIC ACID) FROM PRECISION CHROME, INC., LOCATED IN FOX LAKE, IL, IN ORDER TO PRODUCE CLEANING AGENTS. OPERATINGS BEGAIN IN APPROXIMATELY 1987 AND CEASED IN APPROXIMATELY 1993. THE BUILDING WAS THEN ABANDONED WITH THE HAZARDOUS SUBSTANCES INSIDE. THERE WERE 4 PRPS ASSOCIATED WITH THE SITE AT THE TIME OF THE REMOVAL ACTION. UNDER AN AOC DATED 8/29/95, PRECISION CHROME, INC. AGREED TO DISPOSE OF ITS WASTES LEFT AT THE SITE, AND AGREED TO REIMBURSE U.S. EPA ITS OVERSIGHT COSTS. PRECISION CHROME COULD NOT AFFORD TO PERFORM THE ENTIRE REMOVAL ACTION, AND THIS FACT WAS VERIFIED BY A U.S. EPA REVIEW OF PRECISION CHROME'S SUBMITTED FINANCIAL DOCUMENTS. AFTER THE REMOVAL OF ITS WASTE, PRECISION CHROME REIMBURSED U.S. EPA $40,025.07 IN OVERSIGHT COSTS, AND $342.58 IN INTEREST THAT THAD ACCRUED. U.S. EPA FUNDED THE REMAINDER OF THE REMOVAL ACTION IN THE AMOUNT OF $1,346,154.99 BECAUSE THE REMAINING PRPS WERE NOT FINANCIALLY VIABLE. TWO ADDITIONAL PRPS WERE INCLUDED IN A DEMAND LETTER ISSUED AT THE SAME TIME AS A DEMAND LETTER TO PRECISION CHROME, INC. AT THAT TIME, PRECISION CHROME, INC. NEGOTIATE D A FINAL SETTLEMENT WITH THE AGENCY FOR $95,000.00 A SECOND ABILITY TO PAY ANALYSIS WAS PERFORMED TO VERIFY PRECISION'S CLAIM THAT IT COULD NOT REIMBURSE U.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown