ANTRIM DEVELOPMENT CORPORATION

Administrative - Formal · FY1999 · — · Final Order With Penalty · 31814

$20K
Penalty
Cost recovery
Compliance action

Case

Case Number
05-1999-0508
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

RESPONDENT OPERATED 2 UNDERGROUND INJECTION WELLS IN VIOLATION OF PERMITS. RESPONDENT FAILED TO TIMELY PERFORM MECHANICAL INTEGRITY DEMONSTRATIONS FOR 2 UIC WELLS. RESPONDENT SUBMITTED MIT RESULTS ON 8/11/99. THE OPERATOR DEMONSTRATED AN INABILITY TO PAY AS INDICATED IN THE ABEL ANALYSIS. AFTER MEETING WITH THE OPERATOR IT WAS DETERMINED IF THE OPERATOR WAS ASSESSED THE 76,000 PROPOSED PENALTY IT WOULD BANKRUPT THE COMPANY.

Source

Authoritative
EPA ECHO
Machine