# GENERAL MOTORS CORP - DEFIANCE PLANT
> **Administrative - Formal** · FY1999 · — · Final Order No Penalty
## Case
- **Activity ID:** `31844`
- **Case Number:** 05-1999-0538
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** $100K
- **Multimedia (multi-env):** N
## Defendants
- GENERAL MOTORS CORP - DEFIANCE PLANT (settlement)
## Summary

CONSENT AGREEMENT WITH GM FOR PERFORMANCE OF CORRECTIVE      ACTION ACTIVITIES AT DEFIANCE POWERTRAIN FACILITY.  INCLUDES DEADLINES FOR PERFORMANCE OF ENVIRONMENTAL INDICATORS AND    SUBMITTAL OF PROPOSED FINAL REMEDY.  ORDER IS PERFORMANCE-   BASED AND DIFFERS FROM USUAL MODEL ORDERS.

---