# TRANE CO.
> **Administrative - Formal** · FY1999 · — · Final Order With Penalty
## Case
- **Activity ID:** `31967`
- **Case Number:** 05-1999-0675
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** $20K
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- TRANE CO. (complaint) (settlement)
## Summary

ADMINISTRATIVE COMPLT FILED 9/23/99                          THE TRANE COMPANY PERMANENTLY SHUT DOWN A COAL-FIRED BOILER, WHICH WAS FOUND BY MEANS OF A STACK TEST TO BE VIOLATING     THE WISCONSIN SIP FOR PARTICULATE MATTER.  A SECOND BOILER   WAS CONVERTED TO NATURAL GAS.

---