# M METAL SITE
> **Administrative - Formal** · FY2001 · — · Final Order No Penalty
## Case
- **Activity ID:** `33202`
- **Case Number:** 05-2001-0576
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** $0
- **Multimedia (multi-env):** N
## Defendants
- INDIANAPOLIS POWER & LIGHT (settlement)
## Summary

WITHIN 30 DAYS OF THE EFFECTIVE DATE OF THIS AGREEMENT, THE  SETTLING PARTY, INDIANAPOLIS POWER & LIGHT, SHALL PAY TO THE EPA HAZARDOUS SUPERFUND $73,412.00 IN REIMBURSEMENT OF PAST  RESPONSE COSTS.  IN ADDITION TO THE INTEREST $500.00 PER     VIOLATION PER DAY THAT SUCH PAYMENT IS LATE.  PENALTIES      SHALL  ACCRUE AS REGARDLESS OF WHETHER EPA HAS NOTIFIED THE  SETTLING PARTY OF THE VIOLATION OR MADE A DEMAND FOR PAYMENT

---