# GARY TAR PIT UNILATERAL ADMIN ORDER (CERCLA)
> **Administrative - Formal** · FY2002 · — · —
## Case
- **Activity ID:** `33427`
- **Case Number:** 05-2002-0075
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** —
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- AMERICAN PREMIER (settlement)
- DOVIE HOUSE (settlement)
- GARY TAR PIT (settlement)
- THE ESTATE OF ARNOLD HOUSE (settlement)
- UNDERWRITERS ARNOLD HOUSE (settlement)
## Summary

THIS ORDER REQUIRES THE RESPONDENTS, AMERICAN PREMIER UNDER- WRITERS ARNOLD HOUSE AND/OR THE ESTATE OF ARNOLD HOUSE,      DOVIE HOUSE, TO CONDUCT REMOVAL ACTIVITIES TO ABATE AN       IMMINENT AND SUBSTANTIAL ENDANGERMENT TO THE PUBLIC HEALTH,  WELFARE OF THE ENVIRONMENT THAT MAY BE PRESENTED BY THE      ACTUAL OR THREATENED RELEASE OF HAZARDOUS SUBSTANCES AT OR   FROM THE SITE.  RESPONDENTS SHALL REIMBURSE U.S. EPA, UPON   WRITTEN DEMAND, FOR ALL RESPONSE COSTS INCURRED BY THE       UNITED STATES IN OVERSEEING RESPONDENTS' IMPLEMENTATION OF   THE REQUIREMENTS OF THIS ORDER.  VIOLATION OF ANY PROVISION  OF THIS ORDER MAY SUBJECT RESPONDENTS TO CIVIL PENALTIES OF  UP TO $27,500 PER VIOLATION PER DAY.

---