- **Activity ID:** `33857`
- **Case Number:** 06-1984-0074
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unknown
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- GNB BATTERIES (complaint)
## Summary

THE CASE WAS REFERRED TO EPA BY THE TDWR FOR ENFORCEMENT     ACTION.  THE VIOLATIONS CITED IN THIS ORDER WERE FIRST DIS-  COVERED DURING THE AUG 15, 1983 INSPECTION.  TDWR HAS BEEN   WORKING WITH THE FACILITY TO BRING THEM INTO COMPLIANCE.     TDWR OBTAINED A SINGED CONSENT AGREEMENT FROM THE FACILITY   ON MARCH 21, 1983.  TO DATE THE FACILITY IS STILL NOT IN     FULL COMPLIANCE AND HAVE NOT FOLLOWED TO CONSENT AGREEMENT.  *                                                            C.O. ASSESSING PENALTY OF $63,125.

---