← EPA enforcement cases

PRINCE MINERALS, INC

Administrative - Formal · FY2013 · — · Final Order With Penalty · 3400044411

Penalty
Cost recovery
Compliance action

Case

Case Number
03-2013-0029
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

AT THE TIME OF EPA'S COMPLIANDCE INSPECTION, EPA DETERMINED THAT RESPONDENT HAD VIOLATED CONDITION 3.4.2 OF ITS SYNTHETIC PERMIT, IN THAT THREE (3) PILES OF CONSTRUCTION/PROCESS MATERIAL WERE NOT COVERED AS REQUIRED.