Administrative - Formal · FY2013 · — · Final Order With Penalty · 3400090119

Penalty
Cost recovery
Compliance action

Case

Case Number
04-2013-5504
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

3/26/2013 - CONSENT AGREEMENT AND FINAL ORDER ISSUED, ASSESSING A PENALTY OF $30,000. RESPONDENT SHALL MAKE PAYMENT WITHIN THIRTY DAYS. ORDER ALLEGES: AT NOT TIME DURING THE DISCHARGE OF DREDGED AND/OR FILL MATERIAL AT THE DISCHARGE AREA FROM ON OR ABOUT MAY 15, 2007, TO ON OR ABOUT MAY 30, 2012, DID RESPONDENT POSSESS A PERMIT AUTHORIZATION UNDER SECTION 404 OF THE CWA, ALLOWING THE ACTIVITIES PERFORMED BY RESPONDENT. THE UNAUTHORIZED DISCHARGES HAVE, THEREFORE, BEEN MADE IN VIOLATION OF SECTION 301(a) OF THE CWA. EACH DISCHARGE BY RESPONDENT OF POLLUTANTS INTO NAVIGABLE WATERS WATERS WITHOUT THE REQUIRED PERMIT ISSUED UNDER SECTION 404 OF THE CWA, IS A VIOLATION OF SECTION 301(a).

Source

Authoritative