# URBAN DRAINAGE & FLOOD CONTROL DIRSTRICT
> **Administrative - Formal** · FY2013 · — · Final Order No Penalty
## Case
- **Activity ID:** `3400153307`
- **Case Number:** 08-2013-0104
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- PAUL HINDMAN (complaint) (settlement)
- URBAN DRAINAGE & FLOOD CONTROL DIRSTRICT (complaint) (settlement)
## Summary

RESPONDENT REVEALED THAT DREDGED AND FILL MATERIAL HAD BEEN DEPOSITED INTO THE CHANNEL OF PINEY CREEK AND ADJACENT WETLANDS.  IT AFFECTED AREA COVERED 2.08 ACRES OF WETLANDS AND 1.01 ACRES OF OPEN WATER WITHIN THE BANKS OF PINEY CREEK.

---