← EPA enforcement cases

General Electric Company et al.

Administrative - Formal · FY2013 · — · Final Order With Specified Cost Recovery · 3400163117

Penalty
Cost recovery
Compliance action

Case

Case Number
02-2013-2008
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Specified Cost Recovery
Multimedia
Self-disclosure
N

Defendants (2)

Summary

On September 30, 2013 EPA and the Respondents signed an administrative settlement agreement and order on consent for performance of a remedial investigation and feasibility study for the groundwater and landfill components of the Dewey Loeffel Landfill Site. In addition, the Respondents will be paying EPA's past response costs and EPA's future oversight costs associated with the landfill and the groundwater RI/FS.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown