# DP&L, O.H. HUTCHINGS GENERATING STATION
> **Administrative - Formal** · FY2013 · — · Final Order With Penalty
## Case
- **Activity ID:** `3400164806`
- **Case Number:** 05-2013-5063
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- DP&L, O.H. HUTCHINGS GENERATING STATION (complaint) (settlement)
## Summary

This case will be resolved simultaneously with a penalty order and administrative consent order.  The penalty order portion of the case does not include a SEP or direct environmental benefits but does provide deterrence of future violations.

---