# CITY OF GENESEE, IDAHO
> **Administrative - Formal** · FY2014 · — · Final Order With Penalty
## Case
- **Activity ID:** `3400169070`
- **Case Number:** 10-2014-0005
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- City of Genesee, Idaho (SB) (complaint) (settlement)
## Summary

The City of Genesee, Idaho operates a wastewater treatment plant which exceeded its NPDES permit limits for biochemical oxygen demand, total suspended solids, pH and E. coli.  On December 30, 2013, EPA Region 10 filed a Consent Agreement and Final Order assessing a penalty of $17,700 against the City for these violations of the Clean Water Act.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*