# PLAINS ALL AMERICAN PIPELINE L.P., aka BAY SPRINGS
> **Administrative - Formal** · FY2013 · — · Final Order No Penalty
## Case
- **Activity ID:** `3400172133`
- **Case Number:** 04-2013-5250
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- PLAINS ALL AMERICAN PIPELINE L.P. aka BAY SPRINGS (settlement)
## Summary

2/9/13 - ADMINISTRATIVE ORDER UNDER 311(c) OF THE CWA ISSUED.  THIS ORDER REQUIRES PERFORMANCE OF REMOVAL ACTIONS IN CONNECTION WITH A FACILITY LOCATED AT OR NEAR AIRPORT ROAD IN HIGHWAY 528 IN BAY SPRINGS, MS. THIS ORDER REUQIRES THE RESPONDENT TO IMMEDIATELY CONDUCT REOVAL OF A DISCHARGE OR TO MITIGATE OR PREVENT A SUBSTANTIAL THREAT OF A DISCHARGE OF OIL.  ON FEB 5, 2013, AT 3:35 P.M., EASTERN TIME, RESPONDENT NOTIFIED THE NATIONAL RESPONSE CENTER OF AN EARLIER SPILL AT OR NEAR RESPONDENT'S PUMP STATION. RESPONDENT'S PIPELINE (AN 8-INCH PIPE) BEGAN DISCHARGING AT LEAST 16,000 GALLONS OF OIL INTO WETLANDS AND INTO AN UNNAMED TRIBUTARY OF PINEY BRANCH, A TRIBUTARY TO THE TALLAHOME CREEK AND/OR THE ADJOINING SHORELINE ACCORDING TO RESPONDENT. THE TALLAHOMA CREEK IS NAVAGABLE WATERS OF THE U.S.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*