Jointa Galusha LLC

Administrative - Formal · FY2014 · — · Final Order No Penalty · 3400203138

Penalty
Cost recovery
Compliance action

Case

Case Number
02-2014-1005
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order No Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

A Compliance Order was issued to the Respondent under Section 113(a)(3) of the Clean Air Act for violations at the company’s Pattens Mills quarry in Fort Ann, New York and its Hartford quarry in Hartford, New York. Both quarries are area sources of hazardous air pollutants and operate reciprocating internal combustion engines (RICE) that failed to meet the May 3, 2013 compliance deadline for the RICE NESHAPs, 40 C.F.R. Part 63, Subpart ZZZZ. The Order establishes a compliance schedule to bring both facilities into compliance by May 3, 2014.