# ALBINA ASPHALT COMPANY - TERMINAL 1
> **Administrative - Formal** · FY2014 · — · Final Order With Penalty
## Case
- **Activity ID:** `3400220537`
- **Case Number:** 10-2014-0086
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Albina Holdings Inc (complaint) (settlement)
- Jeffrey A Arntson, Vice President (Albina Fuel)
## Summary

On July 24, 2014, Region 10 filed an Expedited Settlement Agreement to resolve Spill Prevention, Control and Countermeasure (SPCC) violations at Albina Asphalt Company - Terminal 1 in Vancouver, Washington that occurred in May, 2013.  The facility had a deficient SPCC plan and inadequate secondary containment.  Respondent agreed to pay a penalty of $1,100 and correct the violations within 60 days.

---