# JASPER ALLEN
> **Administrative - Formal** · FY2014 · — · —
## Case
- **Activity ID:** `3400255691`
- **Case Number:** 04-2014-5761
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** —
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- JASPER ALLEN (settlement)
## Summary

6/24/2014 - ADMINISTRATIVE COMPLIANCE ORDER ON CONSENT ISSUED.

ORDER STATES:
COMMENCING ON OR ABOUT DECEMBER 2007, RESPONDENT, AND/OR THOSE ACTING ON BEHALF OF THE RESPONDENT, DISCHARGED DREDGED AND/OR FILL MATERIAL INTO WETLANDS ON THE SITE USING EARTH MOVING MACHINGERY, DURING UNAUTHORIZED ACTIVITIES ASSOCIATED WITH THE CONVERSION OF FORESTED WETLANDS TO BLUEBERRY PRODUCTION. TO DATE, THE UNAUTHORIZED DREDGED AND/OR FILL MATERIAL REMAINS IN WATERS OF THE UNITED STATES.

AT NO TIME DURING THE DISCHARGE OF DREDGED AND/OR FILL MATERIAL INTO THE DISCHARGE AREA FROM DECEMBER 2007, TO THE PRESENT, DID THE RESPONDENT POSSESS A PERMIT UNDER SECTION 404 OF THE CWA, AUTHORIZING THE DISCHARGE OF DREDGED AND/OR FILL MATERIAL BY RESPONDENT. 

THEREFORE, RESPONDENT HAS VIOLATED SECTION 301 OF THE CWA, BY DISCHARGING POLLUTANTS INTO NAVIGABLE WATERS WITHOUT A PERMIT.

ORDER REQUIRES:
RESPONDENT AGREES TO RESTORE THE 3.98 ACRES OF IMPACTED WETLANDS ON THE SITE IN ACCORDANCE WITH THE MAY 2014, RESOLUTION/RESTORATION PLAN. THE RESOLUTION/RESTORATION PLAN INCLUDES REMOVAL OF DREDGED AND/OR FILL MATERIAL TO PRE-IMPACT SURFACT ELEVATION AND REPLANTING OF NATIVE TREE SPECIES AT A DENSITY OF 437 TREES PER ACRE.

WITHIN 60 DAYS AFTER RECEIPT OF THE SIGNED AOC, RESPONDENT SHALL COMMENCE WITH REMOVAL OF DREDGED AND/OR FILL MATERIAL.

WITHIN THE FIRST PLANTING SEASON AFTE EXECUTION OF THE AOC, RESPONDENT SHALL COMMENCE WITH PLANTING OF NATIVE TREE SPECIES, AS SPECIFIED.

WITHIN 30 DA

---