# SPRINGFIELD WATER AND SEWER
> **Administrative - Formal** · FY2014 · — · Final Order No Penalty
## Case
- **Activity ID:** `3400289311`
- **Case Number:** 01-2014-2521
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- SPRINGFIELD WATER AND SEWER (settlement)
## Summary

The Springfield Water and Sewer Commission submitted an integrated wastewater plan which covers CSO collection system and treatment plant work for the next 25+ years for the City of Springfield, MA. This is an order to have the commission do phases 2 and 3 of the CSO work outlined in the integrated plan.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*