# Hill Brothers ESA (CAA 112R)
> **Administrative - Formal** · FY2014 · — · Final Order With Penalty
## Case
- **Activity ID:** `3400295414`
- **Case Number:** 09-2014-3510
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Dave Hernandez (complaint) (settlement)
- Hill Brothers (complaint) (settlement)
## Summary

This is an Expedited Settlement Agreement between USEPA and Hill Brothers in City of Industry, CA (respondent), for alleged violations of the Clean Air Act, Section 112(r) Risk Management Plan regulations. Respondent agrees to Settle for a penalty of $2,340.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*