← EPA enforcement cases

SOLDOTNA Y CHEVRON - ESA Pilot

Administrative - Formal · FY2015 · — · Final Order With Penalty · 3400296668

Penalty
Cost recovery
Compliance action

Case

Case Number
10-2015-0011
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

On November 18, 2014, Region 10 filed an Expedited Settlement Agreement and Final Order (ESA) with Mark Rozak, the owner and operator of underground storage tanks (USTs) at Soldotna Y Chevron, in Soldotna, AK. The ESA requires Soldotna Y Chevron to pay a $10,390 penalty for 4 violations, including failure to provide release detection for tanks and piping and failure to equip pressurized piping with an automatic line leak detector. Soldotna Y Chevron is also required to submit documentation of release detection for the five tanks for July-November, 2014.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown