# MONTANA DE FIBRA
> **Judicial** · FY1986 · — · Final Order With Penalty
## Case
- **Activity ID:** `34005`
- **Case Number:** 06-1986-0019
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** $58K
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- MONTANA DE FIBRA (complaint) (settlement)
## Summary

THE VIOLATIONS UPON WHICH THIS ACTION IS BASED:              1: FAILURE TO HAVE PSD PERMIT AS REQUIRED BY 40 C.F.R. 52.21 2: FAILURE TO CONDUCT PERFORMANCE TEST IN COMPLIANCE W/STATE    PERMIT 526.                                               3: FAILURE TO LIMIT EMISSIONS IN ACCORDANCE W/STATE PERMIT      526.                                                      THE PROPOSED RELIEF TO BE SOUGHT IS THE RECOVERY OF A CIVIL  PENALTY OF NO LESS THAN $203,826, BUT NO GREATER THAN        $25,000 PER DAY FOR EACH DAY OF VIOLATION.

---