DATA SHEET: * VIOLATIONS: J. PIZZUTO CO., INC. HAS VIOLATED THE ASBESTOS NESHAP REGULATIONS FOUND AT 40 CFR PART 61, SUBPART M DURINT ITS DEMOLITION ACTIVITIES AT REYNOLDS METALS CO'S HURRICANE CREEK PLANT LOCATED IN BAUXITE, ARKANSAS. AS SUCH, J. PIZZUTO CO, INC. HAS VIOLATED SECTION 112(C) OF THE CAA. IN ADDITION, REYNOLDS METALS CO, AS THE 'OWNER' OF THE SITE, IS ALSO LIABLE FOR THE ASBESTOS NESHAP VIOLATIONS. * PROPOSED RELIEF: CIVIL PENALTY TO REQUIRE J. PIZZUTO COMPANY, INC. AND/OR REYNOLDS METAL COMPANY TO PAY A CIVIL PENALTY FOR PAST VIOLATIONS OF THE CAA. * RECENT CONTACTS: ON JUNE 7, 1988, THE ADPC&E NOTIFIED J. PIZZUTO CO, INC. OF ASBESTOS NESHAP VIOLATIONS DISCOVERED DURING A STATE INSPEC- TION OF DEMOLITION ACTIVITIES BEING CONDUCTED BY J. PIZZUTO CO AT THE HURRICAN CREEK PLANT. EPA REGON VI HAS RECENTLY SPOKEN TO COUNSEL FOR J. PIZZUTO CO ABOUT POTENTIAL SETTLE- MENT OF THIS CASE. * ISSUES: