← EPA enforcement cases

BP Cherry Point Refinery

Administrative - Formal · FY2015 · — · Final Order With Penalty · 3600028973

Penalty
Cost recovery
Compliance action

Case

Case Number
10-2015-0003
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

On October 28, 2014, Region 10 filed an expedited settlement agreement which both initiated and concluded an administrative action against the BP West Coast Products LLC facility in Blaine, Washington for violations of CAA ? 112(r) Risk Management Program requirements. The Region alleged that the company failed to comply with several risk management program requirements that apply to its use of flammable mixtures containing propane, pentane, butane, and isobutane. The violations have been corrected. Under the terms of the agreement, the company agreed to pay $4,500

Source

Authoritative
EPA ECHO
Machine